Showroom Construction Cost Estimator
Plan a car, two-wheeler, furniture, electronics or fashion showroom from its display floor, workshop and back areas. See the facade, services, equipment and the full cost with land, finance and taxes, display capacity, materials, stage-wise cash flow and an editable measurement sheet.
A. Land
- Not entered—Add land cost in the form to include it
- Land and legal₹00.0% of total, ₹0 per sq.ft.
B. Building, facade, systems and site
- Building at base rate₹3,71,69,00012,800 sq.ft., zone-weighted at ₹2,900 average
- Facade and finishes₹50,73,000Details in the Facade and systems tab
- Systems₹58,12,000Details in the Facade and systems tab
- Workshop equipment₹71,00,000Details in the Facade and systems tab
- Site₹27,50,000Details in the Facade and systems tab
- Utility connections (1.5%)₹5,58,000Electricity load, water and sewer
- Hard cost₹5,84,61,00080.5% of total, ₹4,570 per sq.ft.
C. Fees and approvals
- Design and consultants (5%)₹29,23,000
- Permissions and fire NOC (2%)₹11,69,000
- Project management (3%)₹17,54,000
- Insurance (0.25%)₹1,46,000Contractor all-risk cover
- Legal and administration (0.5%)₹2,92,000
- Soft cost₹62,85,0008.7% of total, ₹490 per sq.ft.
D. Risk, taxes and finance
- Price escalation (0% a year)₹0On hard cost over half of 17 months
- GST on contractor billsoffSwitch on if you cannot claim it back
- Contingency (8%)₹51,80,000
- Interest during construction₹27,24,000₹3,49,63,000 loan at 11% for 17 months, half drawn on average
- Risk, taxes and finance₹79,04,00010.9% of total, ₹620 per sq.ft.
- Total project cost₹7,26,50,000₹5,680 per sq.ft. without land
- Substructure (excavation, foundation)₹37,17,00010% of building cost, ₹290 per sq.ft.
- RCC or steel frame₹89,20,00024% of building cost, ₹700 per sq.ft.
- Masonry and plaster₹29,73,0008% of building cost, ₹230 per sq.ft.
- Flooring₹29,73,0008% of building cost, ₹230 per sq.ft.
- Doors, rolling shutters, glazing₹37,17,00010% of building cost, ₹290 per sq.ft.
- False ceiling₹22,30,0006% of building cost, ₹170 per sq.ft.
- Painting₹14,87,0004% of building cost, ₹120 per sq.ft.
- Electrical and display lighting₹52,04,00014% of building cost, ₹410 per sq.ft.
- Plumbing, toilets, drains₹18,58,0005% of building cost, ₹150 per sq.ft.
- Waterproofing₹7,43,0002% of building cost, ₹60 per sq.ft.
- Interior fit-out₹18,58,0005% of building cost, ₹150 per sq.ft.
- Preliminaries and site overheads₹14,87,0004% of building cost, ₹120 per sq.ft.
- Building₹3,71,69,00012,800 sq.ft.
A typical split of showroom building cost by trade. Facade, air-conditioning, equipment and site works are listed separately.
Quantities come from the measurement sheet below, so they change with the towers and with your sheet edits. Change a rate or a sheet quantity and the construction cost, stages, towers and total all update.
- Core civil materials₹1,39,34,00037% of construction cost
- Other construction cost₹2,32,34,000Labour, electrical and plumbing materials, doors, windows, fittings, formwork, equipment and contractor overheads
- Building construction₹3,71,69,000Materials plus other cost
- Change from your rates and sheet edits+₹0Default materials ₹1,39,34,000, now ₹1,39,34,000. This change flows into every cost, stage, zone and the total.
- Total project cost₹7.26 crore
Per cum of RCC: 8 bags cement, 0.45 cum sand, 0.9 cum aggregate, 115 kg steel. Per cum of brick masonry: 500 bricks, 1.25 bags cement, 0.3 cum sand. Plaster 0.12 bag cement per sq.m. Paint 0.2 litre per sq.m. inside and 0.25 outside for two coats. Custom sheet rows are not included.
1. Design and brand approval₹36.8 LMonth 1 to 2, 5.1% of total, 5% spent by the end
- Design and consultants₹20,46,000
- Contingency₹6,09,000
- Permissions and fire NOC₹3,51,000
- Interest during construction₹3,20,000
- Project management₹2,06,000
- Legal and administration₹1,46,000
2. Permissions and site set-up₹35.5 LMonth 3 to 4, 4.9% of total, 10% spent by the end
- Design and consultants₹8,77,000
- Permissions and fire NOC₹8,18,000
- Contingency₹6,09,000
- Interest during construction₹3,20,000
- Parking, yard and landscaping₹2,75,000
- Project management₹2,06,000
- Preliminaries and site overheads₹1,49,000
- Insurance₹1,46,000
- Legal and administration₹1,46,000
3. Excavation and foundation₹70.0 LMonth 5 to 7, 9.6% of total, 20% spent by the end
- Substructure (excavation, foundation)₹37,17,000
- Contingency₹9,14,000
- RCC or steel frame₹8,92,000
- Interest during construction₹4,81,000
- Preliminaries and site overheads₹3,72,000
- Project management₹3,10,000
- Waterproofing₹2,23,000
- Plumbing, toilets, drains₹93,000
4. Structure and facade₹1.82 crMonth 8 to 12, 25.1% of total, 45% spent by the end
- RCC or steel frame₹80,28,000
- Facade (structural glazing)₹23,39,000
- Contingency₹15,23,000
- Electrical and display lighting₹13,01,000
- Masonry and plaster₹11,89,000
- Interest during construction₹8,01,000
- Doors, rolling shutters, glazing₹7,43,000
- Preliminaries and site overheads₹5,20,000
- Project management₹5,16,000
- Plumbing, toilets, drains₹4,65,000
- Fire fighting₹4,22,000
- Air-conditioning (VRV / VRF)₹3,96,000
5. Services and interiors₹2.95 crMonth 13 to 16, 40.6% of total, 85% spent by the end
- Electrical and display lighting₹39,03,000
- Doors, rolling shutters, glazing₹29,73,000
- Flooring₹26,76,000
- Facade (structural glazing)₹23,39,000
- False ceiling₹20,07,000
- Service bays (hoists, tools, air lines)₹19,50,000
- Masonry and plaster₹17,84,000
- Air-conditioning (VRV / VRF)₹13,86,000
- Plumbing, toilets, drains₹13,01,000
- Contingency₹12,19,000
- Interior fit-out₹11,15,000
- Parking, yard and landscaping₹11,00,000
- Painting₹10,41,000
- Fire fighting₹8,45,000
- Interest during construction₹6,41,000
- Power backup₹6,14,000
- Project management₹4,13,000
- Waterproofing₹3,72,000
- Preliminaries and site overheads₹3,72,000
- Ceiling upgrade₹3,56,000
- Security system₹3,00,000
- Washing bay₹3,00,000
- Utility connections₹2,79,000
- Brand signage and pylon₹2,40,000
6. Equipment, testing and handover₹1.07 crMonth 17 to 17, 14.7% of total, 100% spent by the end
- Service bays (hoists, tools, air lines)₹45,50,000
- Parking, yard and landscaping₹13,75,000
- Interior fit-out₹7,43,000
- Brand signage and pylon₹5,60,000
- Painting₹4,46,000
- Power backup₹4,10,000
- Contingency₹3,05,000
- Security system₹3,00,000
- Washing bay₹3,00,000
- Flooring₹2,97,000
- Utility connections₹2,79,000
- False ceiling₹2,23,000
- Air-conditioning (VRV / VRF)₹1,98,000
- Interest during construction₹1,60,000
- Waterproofing₹1,49,000
- Fire fighting₹1,41,000
- Project management₹1,03,000
- Preliminaries and site overheads₹74,000
- Ceiling upgrade₹40,000
- Total over 17 months₹7,26,50,000Land in stage 1; fees, contingency, taxes and interest spread by duration
- Display floor per sq.ft.₹6,380
- Workshop and service per sq.ft.₹5,470
- Spares or warehouse per sq.ft.₹3,530
- Offices per sq.ft.₹5,040
- Customer lounge per sq.ft.₹6,660
- Delivery bay per sq.ft.₹6,100
- Display capacity16 carsAt 250 sq.ft. each including walking space
- Service bays13At 450 sq.ft. each
Shared costs follow each zone's weighted building cost; workshop equipment is added to the workshop. Land is not included.
Facade and finishes
- Facade (structural glazing)₹46,77,0003,543 sq.ft. from 120 ft frontage
- Ceiling upgrade₹3,96,0006,000 sq.ft.
Systems
- Air-conditioning (VRV / VRF)₹19,80,0006,000 sq.ft. of customer and office areas
- Fire fighting₹14,08,00012,800 sq.ft.
- Power backup₹10,24,00012,800 sq.ft.
- Security system₹6,00,000
- Brand signage and pylon₹8,00,000
Workshop equipment
- Service bays (hoists, tools, air lines)₹65,00,00013 bays at ₹5 lakh
- Washing bay₹6,00,000
Site
- Parking, yard and landscaping₹27,50,00010,000 sq.ft.
- Facade, systems, equipment, site₹2,07,35,000₹1,620 per sq.ft.
Save the current project as A, change zones, facade or quality, then save it as B to compare.
Measurement sheet
Generated from the building above and updated when you change it. Edit any cell, restore automatic values, add your own rows and download as CSV. Quantity changes flow into materials and the total. All dimensions are in metres.
Quantity = Nos × L × B × H/D for cum, Nos × L × B for sq.m., Nos × L for running metres and Nos alone for numbers.
What makes a showroom different
A showroom is judged from the road. Its frontage, glass and lighting sell before the staff do, and in vehicle showrooms the workshop behind it earns much of the income.
Customer areas cost more
- Display floor, with large column-free spans, bright lighting and premium flooring.
- Customer lounge, fitted like a café or hotel lobby.
- Delivery bay, where new vehicles are handed over.
- Facade, usually glazing or cladding along the full frontage.
Back areas cost less but need equipment
- Workshop, with epoxy floors, drains, hoists and compressed air.
- Spares or warehouse, with racks and simple finishes.
- Offices, for sales, finance and service advisers.
Zone weights: display ×1.15, lounge ×1.20, delivery ×1.10, offices ×1.00, workshop ×0.85, spares ×0.70.
How the showroom cost is built
The building is priced zone by zone. Facade, air-conditioning, finishes upgrades, equipment and site works are separate lines.
Building = each zone's area × base rate × zone weight × location, with the interior factor on customer areas
Facade = frontage × building height × facade rate
Systems = air-conditioning on customer and office areas, flooring and ceiling upgrades, security, signage
Equipment = service bays, washing bay and paint booth for vehicle showrooms
Total = land + building + facade + systems + equipment + site + fees + contingency and finance
- Base rate per sq.ft.Budget ₹2,000Standard ₹2,600Premium ₹3,600
- Facade per sq.ft.Glazing ₹1,200Stone ₹550ACP ₹450Plaster ₹120
- Air-conditioning per sq.ft.Split ₹150VRV ₹300Central ₹350
- Interior factorBasic ×1.00Medium ×1.10High-end ×1.25
- Workshop₹5 lakh a service bayHoist, tools and air line. Washing bay ₹6 lakh, paint booth ₹35 lakh.
Before you build a showroom
Check these early; some decide the layout.
Brand guidelines
Vehicle and franchise brands set facade, signage, flooring and lighting standards, and often approve the drawings before work starts.
Land use and permissions
The plot must allow commercial use; get building permission, a trade licence and a fire NOC where the size or height requires it.
Workshop compliance
Service workshops handle waste oil and wash water, so plan an oil-water separator and apply for pollution control board consent.
Questions
How much does it cost to build a car showroom in India?
With the default 3S car showroom of about 12,800 sq.ft. across display, workshop, spares, offices, lounge and delivery bay, standard quality in a district town, the calculator shows about ₹7.3 crore before land. The glass facade, workshop equipment, air-conditioning and brand signage are large parts of that.
How does the showroom type change the estimate?
Choosing a type loads a typical set of zones, floors, frontage and parking. A car showroom includes a workshop, spares and delivery bay; a furniture showroom has a large display floor and warehouse; electronics and fashion showrooms have smaller back areas. Every area stays editable.
Why is the facade priced separately?
Showroom facades are usually full-height glass or cladding along the road frontage, and they cost far more per sq.ft. than plaster. The calculator multiplies frontage by building height to get the facade area and prices it by the finish you choose.
What is display capacity?
For car and two-wheeler showrooms, the display floor is divided by the space one vehicle needs with walking room around it: about 250 sq.ft. for a car and 40 sq.ft. for a two-wheeler. Workshop bays are worked out the same way. Use it to check whether the area matches the number of vehicles your brand expects.
Are workshop equipment and brand signage included?
Workshop equipment is included for car and two-wheeler showrooms: hoists and tools for each service bay, a washing bay and an optional paint booth. Brand signage and a pylon sign are included when switched on. Showroom furniture supplied by the brand is not included.
Do material rates change the total?
Yes. Material quantities come from the measurement sheet. Change a rate or a sheet quantity and the difference from the default materials flows through construction, fees, contingency, interest, stages, zones and the total.
What approvals does a showroom need?
Usually building permission for commercial use, a fire NOC depending on height and floor area, a trade licence, and for workshops a consent from the pollution control board for waste oil and wash water. Car makers also approve the showroom design against their corporate identity guidelines.
Is my data stored?
No. The calculator runs in your browser, loads no third-party scripts and does not ask for contact details. Inputs leave the page only if you copy the link, share on WhatsApp or download the CSV.