Concrete Mix Ratio Calculator

Pick a grade or type your own ratio, enter the volume or the size of your slab or column, and get the cement bags, sand, aggregate and water, how much to put in each mixer batch, and the cost.

Updated Rates reviewed September 2026

Built by Bhavin Sheth Runs in your browser, no sign-up

1. Grade and mix ratio Nominal mix, water-cement 0.5

1 : 1.5 : 38.1 bags per cum

2. How much concrete? 3.48 cum = 123 cft

Slab: length × width × thickness (mm). Round column: diameter (mm) × height. Or enter a volume in cum directly. Count multiplies the row.

3. Mixing

4. Rates Change to your local prices

Set labour to 0 to see materials only. 1 cum = 35.3 cft; 1 brass = 100 cft.

1Compare

Your volume in every grade

The same concrete worked out in each nominal mix, with your rates, so you can see what a higher grade costs.

GradeMixCement bagsSand cumAggregate cumWater LTotalPer cum
M51:5:10101.713.42300₹20,836₹5,981
M7.51:4:8131.683.37390₹21,841₹6,269
M101:3:6161.643.28440₹22,729₹6,524
M151:2:4231.563.13633₹24,951₹7,162
M201:1.5:3291.492.98725₹26,825₹7,700
M251:1:2401.372.74900₹30,305₹8,699

2On site

What goes into one bag of cement

Site mixing is done by the bag. A 35 litre gauge box (farma) holds about the same volume as one 50 kg bag, so the ratio numbers tell you how many boxes of sand and aggregate to add.

GradeSand per bagAggregate per bagGauge boxesWater per bagConcrete per bag
M5 (1:5:10)6.13 cft12.25 cft1 : 5 : 1030 L0.361 cum
M7.5 (1:4:8)4.90 cft9.80 cft1 : 4 : 830 L0.293 cum
M10 (1:3:6)3.68 cft7.35 cft1 : 3 : 628 L0.225 cum
M15 (1:2:4)2.45 cft4.90 cft1 : 2 : 428 L0.158 cum
M20 (1:1.5:3)1.84 cft3.68 cft1 : 1.5 : 325 L0.124 cum
M25 (1:1:2)1.23 cft2.45 cft1 : 1 : 223 L0.090 cum

3Grades

Nominal mix or design mix: which grade can you make on site?

The grade is the strength after 28 days in N/mm². Nominal ratios are a safe, simple way to reach low and medium grades on site; above M20 a lab design mix or ready-mix concrete is the reliable route.

M5 and M7.5

1:5:10 · 1:4:8

Use for: lean concrete below footings, levelling and filling.

Not for: anything that carries load or has steel.

M10 and M15

1:3:6 · 1:2:4

Use for: PCC under floors, paths, steps, plain concrete floors.

Not for: slabs, beams or columns.

M20

1:1.5:3

Use for: RCC slabs, beams, columns and footings of houses in mild conditions.

Watch: the highest grade allowed by nominal mix under IS 456.

M25

1:1:2 as a guide

Use for: RCC exposed to rain, soil or water, taller buildings.

Watch: order as design mix or ready-mix; the ratio here only estimates quantity.

Water-cement ratioLess water, stronger concrete; never add water to ease pouring
CompactionVibrate or rod well to remove air pockets
CuringKeep wet for at least 7 days, longer with PPC
MeasuringUse gauge boxes, not head pans, for sand and aggregate

The drawings decide the grade. Use the grade your structural engineer specified; a richer ratio on site cannot make up for poor curing or too much water.

4Method

How the quantities are worked out

The dry volume method used on Indian sites.

Wet volume = count × length × width × thickness
Dry volume = wet volume × 1.54
Cement = dry × c ÷ (c + s + a); bags = cum ÷ 0.0347
Sand = dry × s ÷ (c + s + a)
Aggregate = dry × a ÷ (c + s + a)
Water = bags × 50 kg × water-cement ratio
Per bag = 0.0347 cum × s ÷ c of sand, × a ÷ c of aggregate
  1. Volumes, not weights. Nominal ratios are by volume. Design mixes use weights and need a lab.
  2. Moist sand bulks. Damp sand takes up to a quarter more space, so add more by volume when it is wet.
  3. Steel takes little room. Reinforcement is 1 to 2% of volume and is covered by wastage.

5Scope

What this calculator does and does not do

Knowing the limits helps you add the right margin before you place an order.

It does

  • Work out cement, sand, aggregate and water for any grade or ratio
  • Find the volume of slabs, rectangles and round columns
  • Tell you what to add to each bag and how many batches
  • Price materials, labour and mixer, per cum
  • Compare all grades for the same volume
  • Give an order list, CSV, shareable link and print

It does not

  • Design a concrete mix or adjust for admixtures
  • Correct for moisture in sand or aggregate
  • Include steel, shuttering or curing
  • Price ready-mix concrete, pumping or transport
  • Know your local prices; change the rates to match your supplier

6FAQ

Questions

What is the mix ratio of M20 concrete?

The nominal mix for M20 is 1 : 1.5 : 3, meaning one part cement, one and a half parts sand and three parts coarse aggregate by volume. For one cubic metre of finished concrete that is about 8.1 bags of cement, 0.42 cum of sand and 0.84 cum of aggregate before wastage.

What are the mix ratios of M5, M7.5, M10, M15 and M25?

Common nominal mixes are M5 1:5:10, M7.5 1:4:8, M10 1:3:6, M15 1:2:4, M20 1:1.5:3 and M25 1:1:2. M25 and higher grades should be made from a lab design mix, so treat 1:1:2 only as a guide.

Why is the dry volume 1.54 times the wet volume?

Loose cement, sand and aggregate contain air gaps. When water is added and the mix is compacted, the gaps fill and the volume shrinks by roughly a third, so about 1.52 to 1.57 cum of dry material makes 1 cum of concrete. The calculator uses 1.54 and lets you change it.

How much sand and aggregate should go with one bag of cement?

Multiply the ratio numbers by the volume of one bag, about 0.0347 cum or 1.23 cft. For M20 that is about 1.84 cft of sand and 3.68 cft of aggregate per bag. A 35 litre gauge box holds about one bag's volume, so M20 is one bag, one and a half boxes of sand and three boxes of aggregate.

How much water is needed per bag?

Water = cement weight × water-cement ratio. At 0.5, a 50 kg bag needs 25 litres. Lower ratios give stronger, more durable concrete but need better compaction; do not add extra water on site to make it easier to pour.

What is the difference between nominal mix and design mix?

A nominal mix uses fixed volume ratios such as 1:1.5:3, measured on site. A design mix is worked out in a lab for your cement, sand and aggregate, by weight, to reach a target strength with less cement. IS 456 allows nominal mixes only up to M20.

What is a brass?

A brass is 100 cubic feet, about 2.83 cubic metres. Sand and aggregate are shown in cum, cft and brass.

Is my data stored?

No. The calculator runs in your browser and loads no third-party scripts. Inputs leave the page only if you copy the link, share on WhatsApp or download the list.